home *** CD-ROM | disk | FTP | other *** search
/ Apple Reference & Presen…rary 6 (Reseller Edition) / Apple Ref. & Pres. Lib.v6.0.toast / pc / 5-Fonts & Software / Applications / MacProject II / MacProject II Help / card_38807.txt < prev    next >
Text File  |  1989-09-27  |  2KB  |  65 lines

  1. -- card: 38807 from stack: in
  2. -- bmap block id: 0
  3. -- flags: 0000
  4. -- background id: 3633
  5. -- name: Task and Resource Durations
  6.  
  7.  
  8. -- part 36 (field)
  9. -- low flags: 01
  10. -- high flags: 0002
  11. -- rect: left=409 top=260 right=275 bottom=464
  12. -- title width / last selected line: 0
  13. -- icon id / first selected line: 0 / 0
  14. -- text alignment: 1
  15. -- font id: 3
  16. -- text size: 10
  17. -- style flags: 0
  18. -- line height: 13
  19. -- part name: pagexofy
  20.  
  21.  
  22. -- part 37 (button)
  23. -- low flags: 00
  24. -- high flags: A003
  25. -- rect: left=15 top=206 right=227 bottom=211
  26. -- title width / last selected line: 0
  27. -- icon id / first selected line: 0 / 0
  28. -- text alignment: 1
  29. -- font id: 3
  30. -- text size: 10
  31. -- style flags: 0
  32. -- line height: 13
  33. -- part name: Setting Task Durations
  34. ----- HyperTalk script -----
  35. on mouseUp
  36.   go card id 114896
  37. end mouseUp
  38.  
  39.  
  40. -- part contents for background part 6
  41. ----- text -----
  42. Duration is the amount of working time required for a task. There are two types of durations in a project: task durations and resource durations.
  43.  
  44. A task duration is the amount of working time the task as a whole will take. You supply this information yourself, based on your knowledge of the situation and experience with similar tasks.
  45.  
  46.  
  47.  
  48. -- part contents for background part 7
  49. ----- text -----
  50. A resource duration is the amount of working time a resource will spend on the task. 
  51.  
  52. MacProject II determines resource duration, based on information you provide about the resource: the total units of work needed to complete the resource‚Äôs part of the task, the quantity of the resource, and the percentage of the resource‚Äôs available time that will be spent on the task (as specified by its calendar).
  53.  
  54.  
  55. -- part contents for background part 27
  56. ----- text -----
  57. Schedule Information
  58.  